Small towns, big infrastructure: How W3C is building a regional water future in rural Florida

5

minute read

Murray Hamilton, Jr., CPA

Murray Hamilton, Jr., CPA

Vice President

mhamilton@raftelis.com

The Town of Bronson, the Town of Otter Creek, and Cedar Key Water and Sewer District do not have much in common with the large urban utilities that dominate conversations about regional water infrastructure. They are small, rural, and work with limited resources. What they share is a problem too large for any one of them to solve alone: the need for a water treatment plant, a wastewater treatment plant, and 35 miles of water and wastewater mains to serve their communities reliably into the future.

That shared problem became the foundation for the Waccasassa Water and Wastewater Cooperative, known as W3C, and a financial planning effort designed to turn an ambitious infrastructure vision into a fundable, credible plan.

$140 million and a case to make

At a current estimated cost of approximately $140 million, the W3C project is not a small lift for three small member systems. Constructing this infrastructure requires financing through major state and federal programs, including the Florida Department of Environmental Protection's State Revolving Fund (SRF). These programs require demonstrated financial viability: evidence that the cooperative can generate sufficient revenues through member rates to cover operating costs, capital needs, and debt service over time.

Building that case for a cooperative with three small member systems, each with its own rate structures and financial conditions, required both precision and credibility.

A financial forecast built to open doors

Since 2025, Raftelis has served as a subconsultant to the Dewberry project team, developing the financial feasibility evaluations required to support W3C's SRF loan applications. At the core of that work is a 10-year financial forecast projecting revenues generated through member rates, revenue requirements, and the debt service coverage ratios lenders need to see.

The forecast was built to serve multiple purposes. It directly supported the SRF loan applications, providing the specific financial calculations each program required. The same projections were also used to support additional grant funding requests and applications, extending the value of the modeling work beyond a single financing pathway.

Raftelis also prepared an Initial Business Plan, published September 10, 2025, to address the planning phase of the W3C project. The Business Plan established the financial and operational foundation for the cooperative as it evaluates alternative construction scenarios and funding structures. The results of that groundwork are already visible: W3C has secured $800,000 in external funding that the member systems individually would have been unlikely to access on their own.

What cooperation makes possible

The W3C story is still being written. The project is ongoing as Raftelis and the participating communities continue evaluating construction scenarios and funding options. But the early results point to something important: small communities that pool their needs and present a unified, financially credible case can access resources that remain out of reach when they act alone.

For rural utilities facing infrastructure needs that dwarf their individual capacity, the W3C model presents a straightforward premise. Cooperation does not require giving up local identity or control, it requires building the financial foundation that makes larger ambitions achievable. For Bronson, Otter Creek, and Cedar Key, that foundation is now in place.

For more information, contact us.